Dept. of Trans. PROGRESS Serial No. Contract No. 24-018-14-42 04-2K9504 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 26% Location: Federal Project: 04-ALA-5501-0.0/14.4 NONE Progress payment No. 009 Payment period ending: 01-20-24 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,993,117.96 1,055,919.43 2. a. Extra Work 231,723.80 76,598.18 b. Adustment Comp. 3. Materials on Hand 67,275.00 0.00 4. Earned Subject to Retention 7,292,116.76 1,132,517.61 5. Mobilization 6. Total Work Completed 7,224,841.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,292,116.76 1,132,517.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,132,517.61