Dept. of Trans. PROGRESS Serial No. Contract No. 24-109-13-05 04-2K9504 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 34% Location: Federal Project: 04-ALA-5501-0.0/14.4 NONE Progress payment No. 012 Payment period ending: 04-20-24 WALSH CONSTRUCTION COMPANY II LLC 1390 WILLOW PASS RD #950 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,045,278.36 605,162.57 2. a. Extra Work 537,710.20 245,406.51 b. Adustment Comp. 3. Materials on Hand 26,910.00 -13,455.00 4. Earned Subject to Retention 10,609,898.56 837,114.08 5. Mobilization 6. Total Work Completed 10,582,988.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,609,898.56 837,114.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 837,114.08