Dept. of Trans. PROGRESS Serial No. Contract No. 21-259-13-35 04-2Q0604 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 50% Location: Federal Project: 04-SCL-999 NONE Progress payment No. 003 Payment period ending: 09-20-21 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 239,177.50 144,507.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 239,177.50 144,507.50 5. Mobilization 138,375.11 46,125.04 6. Total Work Completed 377,552.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 377,552.61 190,632.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 190,632.54