Dept. of Trans. PROGRESS Serial No. Contract No. 26-166-11-44 04-2Q4204 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 1% Location: Federal Project: 04-SON-116-19.9/33.4 NONE Progress payment No. 002 Payment period ending: 06-20-26 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 259,756.80 251,556.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 259,756.80 251,556.80 5. Mobilization 182,500.00 182,500.00 6. Total Work Completed 442,256.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 442,256.80 434,056.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 434,056.80