Dept. of Trans. PROGRESS Serial No. Contract No. 25-324-12-35 04-2Q5704 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 61% Location: Federal Project: 04-VAR-101-18.7/18.7 ACNH-X085(66) -74).(UPG) Progress payment No. 014 Payment period ending: 11-20-25 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,046,976.00 167,212.00 2. a. Extra Work 1,203,472.13 -34,929.64 b. Adustment Comp. 274,500.00 0.00 3. Materials on Hand 110,167.66 -73,869.29 4. Earned Subject to Retention 8,635,115.79 58,413.07 5. Mobilization 990,000.00 0.00 6. Total Work Completed 9,514,948.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,625,115.79 58,413.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,413.07