Dept. of Trans. PROGRESS Serial No. Contract No. 26-195-10-00 04-2Q7804 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 40% Location: Federal Project: 04-SON-12-19.8 ACNH-P012(133) Progress payment No. 004 Payment period ending: 07-20-26 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 525,292.25 204,144.55 2. a. Extra Work 42,630.53 42,630.53 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 567,922.78 246,775.08 5. Mobilization 99,750.00 0.00 6. Total Work Completed 667,672.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 667,672.78 246,775.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 246,775.08