Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-19-30 04-2Q8004 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 2% Location: Federal Project: 04-SM-92-R12.0/R13.1 CPFL-6204(136) 04-SM-101-10.9/12.4 Progress payment No. 003 Payment period ending: 06-20-25 GORDON N BALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 830,576.10 485,742.30 2. a. Extra Work 43,490.21 34,295.55 b. Adustment Comp. 3. Materials on Hand 63,270.25 28,862.15 4. Earned Subject to Retention 937,336.56 548,900.00 5. Mobilization 6. Total Work Completed 874,066.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 937,336.56 548,900.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 548,900.00