Dept. of Trans. PROGRESS Serial No. Contract No. 26-293-13-47 04-2Q8004 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 47% Location: Federal Project: 04-SM-92-R12.0/R13.1 CPFL-6204(136) 04-SM-101-10.9/12.4 Progress payment No. 019 Payment period ending: 10-20-26 GORDON N BALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,673,771.95 1,226,063.10 2. a. Extra Work 1,598,407.98 157,345.28 b. Adustment Comp. 3. Materials on Hand 27,327.46 -5,287.47 4. Earned Subject to Retention 21,299,507.39 1,378,120.91 5. Mobilization 2,735,000.00 0.00 6. Total Work Completed 24,007,179.93 7. Deductions -13,535.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,020,972.39 1,378,120.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,378,120.91