Dept. of Trans. PROGRESS Serial No. Contract No. 20-041-14-31 04-2Q8404 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 53% Location: Federal Project: 04-SCL-101-38.1/38.1 NONE 04-SCL-880-3.7/3.7 Progress payment No. 005 Payment period ending: 02-10-20 CASE PACIFIC COMPANY 2121 ARDMORE RD PASO ROBLES CA 93446 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 667,576.92 54,698.19 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 667,576.92 54,698.19 5. Mobilization 6. Total Work Completed 667,576.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 667,576.92 54,698.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,698.19