Dept. of Trans. PROGRESS Serial No. Contract No. 04-264-10-50 04-2R1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 60% 04-SM-82-3.5/5.0 Federal Project: 04-SM-82-8.8/9.6 NONE 04-SM-82-10.6/12.3 Progress payment No. 02 Payment period ending: 09-20-04 O C JONES AND SONS INC 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 382,069.95 329,941.55 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 382,069.95 329,941.55 5. Mobilization 39,900.00 18,900.00 6. Total Work Completed 421,969.95 7. Deductions 8. a.Contract Retentions -19,103.50 -13,890.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 402,866.45 334,950.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 334,950.89