Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-241-11-04 04-2R2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SON-1-19.0/25.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 07-21-05 NORTH BAY CONSTRUCTION INC P O BOX 6004 PETALUMA CA 949556004 Escrow No. 02197 Total Estimate This Estimate 1. Contract Itms Without Mobil. 367,778.60 18,628.60 2.a. Extra Work 7,157.21 7,157.21 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 374,935.81 25,785.81 5. Mobilization 6. Total Work Completed 374,935.81 7. Deductions 8. a.Contract Retentions -17,457.50 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 17,457.50 17,457.50 9. Total pay to Contractor 374,935.81 43,243.31 10. Reduction Amt to Escrow -5,000.00 -5,000.00 11. Payment to Escrow 5,000.00 12. Net Pymt. this Estimate 38,243.31