Dept. of Trans. PROGRESS Serial No. Contract No. 05-325-14-21 04-2R2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 80% 04-SM-1-26.3/35.1 Federal Project: 04-SM-1-41.3/42.0 NONE Progress payment No. 06 Payment period ending: 11-20-05 OGRADY PAVING INC 2513 WYANDOTTE ST MOUNTAIN VIEW CA 94043 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 475,588.65 2,185.00 2.a. Extra Work 10,165.44 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 485,754.09 2,185.00 5. Mobilization 6. Total Work Completed 485,754.09 7. Deductions -25,200.00 0.00 8. a.Contract Retentions -24,287.70 -109.25 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 436,266.39 2,075.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,075.75