Dept. of Trans. PROGRESS Serial No. Contract No. 06-324-19-16 04-2R5704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 90% 04-SM-92-R11.8/R11.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-06 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 344,777.00 113,349.00 2.a. Extra Work b. Adjustment Comp. -1,350.00 -1,350.00 3. Materials on Hand 4. Earned Subject to Retention 343,427.00 111,999.00 5. Mobilization 24,000.00 0.00 6. Total Work Completed 367,427.00 7. Deductions 8. a.Contract Retentions -17,171.35 -5,599.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 350,255.65 106,399.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,399.05