Dept. of Trans. PROGRESS Serial No. Contract No. 08-019-08-31 04-2S2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 39% 04-CC-24-0.3/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-08 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 173,733.00 88,250.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 173,733.00 88,250.00 5. Mobilization 66,500.00 14,000.00 6. Total Work Completed 240,233.00 7. Deductions 8. a.Contract Retentions -13,556.96 -5,008.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 226,676.04 97,241.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,241.34