Dept. of Trans. PROGRESS Serial No. Contract No. 08-081-09-32 04-2S2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 65% 04-CC-24-0.3/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 03-20-08 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 389,178.60 125,731.60 2.a. Extra Work 17,426.59 15,606.14 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 406,605.19 141,337.74 5. Mobilization 70,000.00 3,500.00 6. Total Work Completed 476,605.19 7. Deductions 8. a.Contract Retentions -20,330.26 -6,773.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 456,274.93 138,064.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,064.44