Dept. of Trans. PROGRESS Serial No. Contract No. 06-230-07-23 04-2S3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 44% 04-SON-116-9.5/ .0 Federal Project: ER-37A9(4) Progress payment No. 04 Payment period ending: 08-20-06 GORDON N BALL INC 333 CAMILLE AVENUE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 59,566.00 51,250.00 2.a. Extra Work 529.24 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 60,095.24 51,250.00 5. Mobilization 23,750.00 23,750.00 6. Total Work Completed 83,845.24 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 83,845.24 75,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 75,000.00