Dept. of Trans. PROGRESS Serial No. Contract No. 06-293-07-55 04-2S3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 93% 04-SM-84-13.3/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-06 M K M CONSTRUCTION INC P O BOX 2290 CUPERTINO CA 95015 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 97,391.00 63,703.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 97,391.00 63,703.80 5. Mobilization 14,000.00 700.00 6. Total Work Completed 111,391.00 7. Deductions -1,663.00 -83.15 8. a.Contract Retentions -4,869.55 -2,282.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 104,858.45 62,038.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,038.50