Dept. of Trans. FINAL Serial No. Contract No. 07-009-07-26 04-2S4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-ALA-680-2.4/ .0 Federal Project: ER-37A3(4) Progress payment No. 04 Payment period ending: 09-15-06 092106CONSTRUCTION INC P O BOX 2290 CUPERTINO CA 95015 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 191,903.00 0.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 191,903.00 0.00 5. Mobilization 6. Total Work Completed 191,903.00 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 191,903.00 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00