Dept. of Trans. PROGRESS Serial No. Contract No. 08-052-12-17 04-2S5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 04-SM-92-3.6/5.3 Federal Project: NONE Progress payment No. 06 Payment period ending: 02-20-08 GOODWIN CONSTRUCTION INC 460 N YOSEMITE AVE SUITE 4 OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,470.00 28,840.00 2.a. Extra Work b. Adjustment Comp. 32,565.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 404,035.00 28,840.00 5. Mobilization 20,000.00 0.00 6. Total Work Completed 424,035.00 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -20,201.75 -1,442.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 393,833.25 27,398.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,398.00