Dept. of Trans. PROGRESS Serial No. Contract No. 06-230-07-25 04-2S9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 58% 04-SON-128-5.3/5.8 Federal Project: ACST-4390(1) P-4390(1) Progress payment No. 05 Payment period ending: 08-20-06 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,570,224.50 3,028,292.25 2.a. Extra Work 1,972,342.00 374,744.98 b. Adjustment Comp. 252,255.00 126,127.50 3. Materials on Hand 722,941.17 677,122.17 4. Earned Subject to Retention 10,517,762.67 4,206,286.90 5. Mobilization 1,170,000.00 0.00 6. Total Work Completed 10,964,821.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,687,762.67 4,206,286.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,206,286.90