Dept. of Trans. PROGRESS Serial No. Contract No. 21-267-10-32 04-2W1204 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 100% Location: Federal Project: 04-CC-580-6.7/7.8 NONE 04-MRN-580-0.0/2.5 Progress payment No. 006 Payment period ending: 09-24-21 FLATIRON WEST, INC. 2100 GOODYEAR RD BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 1,099,118.78 196,815.61 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,099,118.78 196,815.61 5. Mobilization 6. Total Work Completed 1,099,118.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,099,118.78 196,815.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,815.61