Dept. of Trans. PROGRESS Serial No. Contract No. 21-257-14-32 04-2W3304 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 85% Location: Federal Project: 04-SON-128-16.8/17.6 NONE Progress payment No. 005 Payment period ending: 09-20-21 VALENTINE CORPORATION 111 PELICAN WAY SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 857,862.68 266,006.28 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 857,862.68 266,006.28 5. Mobilization 6. Total Work Completed 857,862.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 857,862.68 266,006.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,006.28