Dept. of Trans. PROGRESS Serial No. Contract No. 22-005-10-45 04-2W3904 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 63% Location: Federal Project: 04-SCL-101-33.2/33.2 NONE Progress payment No. 002 Payment period ending: 12-31-21 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 666,631.03 518,701.73 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 666,631.03 518,701.73 5. Mobilization 6. Total Work Completed 666,631.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 666,631.03 518,701.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 518,701.73