Dept. of Trans. PROGRESS Serial No. Contract No. 25-289-20-57 04-2W4604 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 04-ALA-680-R15.6 NONE Progress payment No. 003 Payment period ending: 10-20-25 SERAFIX ENGINEERING CONTRACTORS INC 7 CROW CANYON CT #250 SAN RAMON CA 94583 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 593,260.00 135,560.00 2. a. Extra Work 1,066.56 0.00 b. Adustment Comp. 3. Materials on Hand 0.00 -30,000.00 4. Earned Subject to Retention 594,326.56 105,560.00 5. Mobilization 6. Total Work Completed 594,326.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 594,326.56 105,560.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,560.00