Dept. of Trans. PROGRESS Serial No. Contract No. 24-110-09-09 04-2W5104 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 39% Location: Federal Project: 04-MRN-101-0.1/0.3 NONE Progress payment No. 001 Payment period ending: 04-20-24 FORT BRAGG ELECTRIC INC PO BOX 1578 FORT BRAGG CA 95437 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 186,670.45 186,670.45 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 186,670.45 186,670.45 5. Mobilization 6. Total Work Completed 186,670.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 186,670.45 186,670.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,670.45