Dept. of Trans. PROGRESS Serial No. Contract No. 26-198-11-31 04-2X7804 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 27% Location: Federal Project: 04-NAP-128-19.1/34.3 NONE Progress payment No. 001 Payment period ending: 07-20-26 PAVEMENT COATINGS CO. PO BOX 849485 LOS ANGELES CA 90084-9485 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 461,734.88 461,734.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 461,734.88 461,734.88 5. Mobilization 6. Total Work Completed 461,734.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 461,734.88 461,734.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 461,734.88