Dept. of Trans. PROGRESS Serial No. Contract No. 24-233-16-10 04-2Y5904 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 7% Location: Federal Project: 04-SM-92-R12.1/R14.5 NONE 04-SM-280-R12.3/R14.5 Progress payment No. 001 Payment period ending: 08-20-24 QA CONSTRUCTORS INC 850 S. VAN NESS AVE #35 SAN FRANCISCO CA 94110 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 259,100.00 259,100.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 259,100.00 259,100.00 5. Mobilization 6. Total Work Completed 259,100.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 259,100.00 259,100.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 259,100.00