Dept. of Trans. PROGRESS Serial No. Contract No. 23-103-19-03 04-2Y9004 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 50% Location: Federal Project: 04-MRN-1-0.0/0.0 NONE Progress payment No. 003 Payment period ending: 03-09-23 BAY AREA TREE SPECIALIST PO BOX 848244 LOS ANGELES CA 90084 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 791,131.86 84,631.49 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 791,131.86 84,631.49 5. Mobilization 6. Total Work Completed 791,131.86 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 791,131.86 84,631.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,631.49