Dept. of Trans. PROGRESS Serial No. Contract No. 14-296-09-46 04-3A23U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 04-SON-101-25.0/29.3 Federal Project: NONE Progress payment No. 25 Payment period ending: 10-20-14 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 25,860,208.85 -109,533.65 2.a. Extra Work 1,281,977.32 187,575.30 b. Adjustment Comp. 84,391.00 -34,000.00 3. Materials on Hand 4. Earned Subject to Retention 27,226,577.17 44,041.65 5. Mobilization 2,800,000.00 0.00 6. Total Work Completed 30,026,577.17 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,006,577.17 44,041.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,041.65