Dept. of Trans. FINAL Serial No. Contract No. 11-073-11-09 04-3A3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SOL-80-38.3/44.7 Federal Project: ACIM-080-2(357) Progress payment No. 07 Payment period ending: 11-30-10 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,793,715.46 0.00 2.a. Extra Work 283,521.07 0.00 b. Adjustment Comp. 338,953.34 0.00 3. Materials on Hand 4. Earned Subject to Retention 11,416,189.87 0.00 5. Mobilization 506,929.00 0.00 6. Total Work Completed 11,923,118.87 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,920,118.87 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00