Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-186-06-58 04-3A3604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-101-5.7/6.1 Federal Project: 04-SM-101-17.3/18.9 NONE Progress payment No. 04 Payment period ending: 06-26-07 AMLAND 3168 KNIGHTS BRIDGE RD SAN JOSE CA 95132 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 807,982.00 243,346.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 807,982.00 243,346.70 5. Mobilization 82,000.00 0.00 6. Total Work Completed 889,982.00 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -28,231.77 0.00 b. Unsatisfactory Prog. 0.00 21,162.39 c. Reduction after 95% Comp. 28,231.77 28,231.77 9. Total pay to Contractor 879,982.00 282,740.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 282,740.86