Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-08-49 04-3A5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 98% 04-ALA-880-3.7/4.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 09-20-12 ROADWAY ENGINEERING WORKS INC 3442 6TH STREET CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 486,145.00 47,461.09 2.a. Extra Work 196,515.98 31,198.80 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 682,660.98 78,659.89 5. Mobilization 6. Total Work Completed 682,660.98 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 682,660.98 78,659.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 78,659.89