Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-08-53 04-3A5904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 63% 63% 04-ALA-13-R9.2/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 07-20-08 COAST CONSTRUCTION INC 4460 REDWOOD HIGHWAY SUITE 16 SAN RAFAEL CA 94903 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 180,571.90 86,276.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 180,571.90 86,276.90 5. Mobilization 11,000.00 550.00 6. Total Work Completed 191,571.90 7. Deductions -1,760.00 -880.00 8. a.Contract Retentions -9,028.60 -3,284.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 180,783.30 82,661.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,661.94