Dept. of Trans. PROGRESS Serial No. Contract No. 09-082-09-01 04-3A7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 52% 04-CC-580-6.1/7.8 Federal Project: 04-MRN-580-0.0/2.6 NONE Progress payment No. 01 Payment period ending: 03-20-09 MANSON CONSTRUCTION CO 200 CUTTING BOULEVARD RICHMOND CA 94804 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,804.00 8,804.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 223,006.00 223,006.00 4. Earned Subject to Retention 231,810.00 231,810.00 5. Mobilization 70,275.00 70,275.00 6. Total Work Completed 79,079.00 7. Deductions 8. a.Contract Retentions -22,934.12 -22,934.12 b. Unsatisfactory Prog. -246.88 -246.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 278,904.00 278,904.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 278,904.00