Dept. of Trans. PROGRESS Serial No. Contract No. 14-016-09-14 04-3A7764 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 69% 04-ALA-80-1.9/8.0 Federal Project: 04-CC-80-0.0/13.5 NONE Progress payment No. 11 Payment period ending: 01-20-14 TABER CONSTRUCTION INC P O BOX 1309 MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,201,204.00 424,181.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,201,204.00 424,181.00 5. Mobilization 420,000.00 0.00 6. Total Work Completed 4,621,204.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,621,204.00 424,181.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 424,181.00