Dept. of Trans. PROGRESS Serial No. Contract No. 15-023-10-49 04-3A7774 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 97% 04-ALA-80-1.9/8.0 Federal Project: 04-CC-80-0.0/13.5 NONE Progress payment No. 18 Payment period ending: 01-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,171,722.19 236,090.70 2.a. Extra Work 428,547.74 80,590.29 b. Adjustment Comp. 260,387.82 13,077.82 3. Materials on Hand 4. Earned Subject to Retention 11,860,657.75 329,758.81 5. Mobilization 425,000.00 0.00 6. Total Work Completed 12,285,657.75 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 65,333.85 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,270,657.75 395,092.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 395,092.66