Dept. of Trans. PROGRESS Serial No. Contract No. 16-029-11-18 04-3A7774 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 97% Location: Federal Project: 04-ALA-80-1.9/8.0 NONE 04-CC-80-0.0/13.5 Progress payment No. 030 Payment period ending: 01-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,773,227.29 0.00 2. a. Extra Work 1,329,551.26 23,785.92 b. Adustment Comp. 1,342,928.38 17,120.27 3. Materials on Hand 4. Earned Subject to Retention 15,445,706.93 40,906.19 5. Mobilization 425,000.00 0.00 6. Total Work Completed 15,870,706.93 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,855,706.93 40,906.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,906.19