Dept. of Trans. PROGRESS Serial No. Contract No. 15-237-14-17 04-3A8704 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 80% Location: Federal Project: 04-CC-680-22.7/24.8 NHPI-6801(71) Progress payment No. 013 Payment period ending: 08-20-15 GOLDEN STATE BRIDGE INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,991,945.97 1,786,995.69 2. a. Extra Work 306,824.13 120,925.25 b. Adustment Comp. 112,503.12 33,801.73 3. Materials on Hand 172,784.06 -84,281.49 4. Earned Subject to Retention 9,584,057.28 1,857,441.18 5. Mobilization 390,000.00 0.00 6. Total Work Completed 9,801,273.22 7. Deductions -6,650.00 -1,650.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 9,967,407.28 1,855,791.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,855,791.18