Dept. of Trans. PROGRESS Serial No. Contract No. 20-021-14-58 04-3A87A4 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 70% Location: Federal Project: 04-CC-680-24.3/24.3 NONE Progress payment No. 034 Payment period ending: 01-20-20 EMPIRE LANDSCAPING INC PO BOX 35 DAVIS CA 95617-0035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 182,355.00 1,360.00 2. a. Extra Work 3,825.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 186,180.00 1,360.00 5. Mobilization 30,000.00 0.00 6. Total Work Completed 216,180.00 7. Deductions -1,422.90 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 214,757.10 1,360.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,360.00