Dept. of Trans. PROGRESS Serial No. Contract No. 16-084-13-41 04-3A9214 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 100% Location: Federal Project: 04-ALA-880-22.6/24.0 NONE Progress payment No. 039 Payment period ending: 03-20-16 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,507,479.68 -90,444.15 2. a. Extra Work 8,442,345.77 260,243.90 b. Adustment Comp. 917,596.85 -9,322.77 3. Materials on Hand 4. Earned Subject to Retention 43,867,422.30 160,476.98 5. Mobilization 3,900,000.00 0.00 6. Total Work Completed 47,767,422.30 7. Deductions -389,319.98 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 47,378,102.32 160,476.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,476.98