Dept. of Trans. PROGRESS Serial No. Contract No. 12-020-08-22 04-3A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 31% 75% 04-SCL-101-47.9/52.2 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-12 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,650.00 28,825.00 2.a. Extra Work 14,895.00 14,895.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 216,545.00 43,720.00 5. Mobilization 90,750.00 0.00 6. Total Work Completed 307,295.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -4,372.00 -4,372.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 302,923.00 39,348.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 39,348.00