Dept. of Trans. PROGRESS Serial No. Contract No. 12-117-08-24 04-3A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 98% 04-SCL-101-47.9/52.2 Federal Project: NONE Progress payment No. 07 Payment period ending: 04-20-12 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 416,234.10 39,799.10 2.a. Extra Work 28,177.83 3,938.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 444,411.93 43,737.66 5. Mobilization 114,950.00 0.00 6. Total Work Completed 559,361.93 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 549,361.93 53,737.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,737.66