Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-150-15-28 04-3A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SCL-101-47.9/52.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 05-04-12 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 796,884.10 380,650.00 2.a. Extra Work 298,925.34 270,747.51 b. Adjustment Comp. -374,041.66 -374,041.66 3. Materials on Hand 4. Earned Subject to Retention 721,767.78 277,355.85 5. Mobilization 121,000.00 6,050.00 6. Total Work Completed 842,767.78 7. Deductions -1,000.00 9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 841,767.78 292,405.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 292,405.85