Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-215-08-48 04-3A9804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SCL-101-47.9/52.2 Federal Project: NONE Progress payment No. 10 Payment period ending: 05-04-12 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 796,884.10 0.00 2.a. Extra Work 396,050.38 5,533.13 b. Adjustment Comp. -105,041.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,087,893.42 5,533.13 5. Mobilization 121,000.00 0.00 6. Total Work Completed 1,208,893.42 7. Deductions -1,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,207,893.42 5,533.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,533.13