Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-10-25 04-3E1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 83% 04-ALA-185-5.3/5.7 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-12 C F ARCHIBALD PAVING INC P O BOX 37 REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 299,793.13 299,793.13 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 299,793.13 299,793.13 5. Mobilization 6. Total Work Completed 299,793.13 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 299,793.13 299,793.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 299,793.13