Dept. of Trans. PROGRESS Serial No. Contract No. 14-142-07-37 04-3E3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 86% 04-SCL-101-R5.0/R17.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-20-14 FBD VANGUARD CONSTRUCTION INC 651 ENTERPRISE COURT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 675,209.00 483,122.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 675,209.00 483,122.00 5. Mobilization 37,000.00 1,850.00 6. Total Work Completed 712,209.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 712,209.00 484,972.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 484,972.00