Dept. of Trans. PROGRESS Serial No. Contract No. 14-168-08-45 04-3E3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 50% 04-SM-82-20.8/22.4 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-20-14 CENTRAL VALLEY ENGNEERING & ASPHALT INC 216 KENROY LANE ROSEVILLE CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 416,486.05 416,486.05 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 416,486.05 416,486.05 5. Mobilization 6. Total Work Completed 416,486.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 416,486.05 416,486.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 416,486.05