Dept. of Trans. PROGRESS Serial No. Contract No. 15-321-10-53 04-3E4204 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 91% Location: Federal Project: 04-SCL-35-14.1/17.1 NONE Progress payment No. 004 Payment period ending: 11-20-15 G. BORTOLOTTO & COMPANY, INC. 582 BRAGATO RD SAN CARLOS CA 94070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 864,481.76 0.00 2. a. Extra Work 7,272.23 7,272.23 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 871,753.99 7,272.23 5. Mobilization 6. Total Work Completed 871,753.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 871,753.99 7,272.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,272.23