Dept. of Trans. PROGRESS Serial No. Contract No. 14-261-13-51 04-3E4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 8% 04-SF-101-R4.3/R4.3 Federal Project: 04-SF-280-R6.7/R6.7 NONE 04-SM-1-20.8/20.8 Progress payment No. 01 Payment period ending: 09-20-14 WESTERN STRUCTURES 6005 TYLER ST RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,829.80 18,829.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 18,829.80 18,829.80 5. Mobilization 6. Total Work Completed 18,829.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,829.80 18,829.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,829.80