Dept. of Trans. PROGRESS Serial No. Contract No. 15-027-07-48 04-3E4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 89% 04-SF-101-R4.3/R4.3 Federal Project: 04-SF-280-R6.7/R6.7 NONE 04-SM-1-20.8/20.8 Progress payment No. 05 Payment period ending: 01-20-15 WESTERN STRUCTURES 6005 TYLER ST RIVERSIDE CA 92503 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 417,118.09 233,684.54 2.a. Extra Work 39,882.67 39,882.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 457,000.76 273,567.21 5. Mobilization 55,000.57 2,750.03 6. Total Work Completed 512,001.33 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 1,099.24 c. Reduction after 95% Comp. 9. Total pay to Contractor 512,001.33 277,416.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 277,416.48